Tuesday 18 August 2009

The End


That's it folks

Thursday 23 April 2009

Nearly











Nearly











Here's some more pics




Sunday 19 April 2009

The Final Week











Nearly there- Carpets & wooden floors this week, a little more painting & that's it We're moving back in on Saturday.

2 Weeks to go







the last 2 weeks of living in Elephant & Castle. Finally we're almost there!

Tuesday 24 March 2009

We're nearly there!





We're almost there - finally it's only taken 2.5 years to get there!! All of the flooring has been brought, well apart from the carpets. All they have to do now is plaster everywhere, then it's the painting and that pretty much it. So the finish date of 17th April is looking like it might happen.


Monday 16 March 2009

Week 7 or 8






It doesn't look as if the Builders have done much over the last couple of weeks, the electrician has been in for the 1st fix, the bathroom & Kitchen has been delivered, so the next phase will be the floor in the Kitchen & plastering everywhere. We're still aiming for a finish date of the 17th April.

Sunday 1 March 2009

Walking


Sarah thought that this would be ideal for me when I go hiking in the Mountains!!!! I don't think so

Week 6






The Kitchen & Bathroom. Everything is pretty much ordered - Kitchen, bathroom, wooden floors - the only issue we have is the carpet. We found an amazing carpet, but typical of Sarah it's the most expensive!!

Week 6




So the builders reckon that they will finish 2 weeks early - mmmmm not too sure if that's going to be possible.
The roof in the kichen is pretty much finish & the Bathroom is almost there.




Friday 20 February 2009

Week 5




The Kitchen

Week 5




The Bathroom.

Week 5




Week 5 and the builders are about 2 weeks ahead of shedule - what are the chances of that!!


Friday 13 February 2009

week 4







Week 4







The Lonesome Toilet


Friday 6 February 2009

Friday 30 January 2009

Week 2





Digging the foundations





Week 2





The kitchen & bathroom.